How the model works
  • The ship is divided into bays, rows and tiers on deck and in the hold; the bow and stern bays have fewer rows and tiers. On arrival the stacks are filled at random to the given share.
  • Containers for one port are stowed together, so whole bays are discharged from the top down. Loading fills free slots from the bottom up; the hold only when the bay's deck is empty.
  • Each bay is worked in the standard sequence: discharge the deck, remove the hatch covers, discharge and load the hold, replace the covers, load the deck.
  • Bays are split between the cranes into contiguous zones with the smallest maximum workload. Cranes never come closer than the given distance; waiting for a neighbour is counted as interference.
  • Several identical ships can lie at the quay. A crane is plugged into a power pit in the middle of its zone and travels no further from it than the cable length. A crane's zone may extend onto the neighbouring ship; when a crane has finished its own bays, it takes the last bay of its left neighbour if the cable reaches it.
  • The cycle time is the trolley travel to the row, hoisting to the slot and to the truck, and positioning with lock / unlock; random variation and the wait for transport are added to it.
  • Results are averaged over the replications: berth and crane productivity (gross over the ship's time at berth, net over the crane's working time) and crane utilization.